Far North Construction has been making a lot of progress on the landlord work for the space! The dividing wall between our space and the other half is finished, the bathrooms have framed walls, plumbing, sewer and electrical. They’re currently estimating 2 more weeks to get all of the finish work done in the bathrooms…tile, toilets & partitions, sinks and countertops.
And then we take possession, and start all of our finishing work!
7/14
7/14 Front of House – Not much new in front7/14 Back of House – Framing for the bathrooms has started!
7/16
7/16 Front of House – Drywall is up on our side.7/10 Back of House – Drywall is up and the sewer lines are extended to where the sinks will be
7/17
7/17 Front of House – No major changes7/17 Back of House – Water lines are in, as is electrical7/17 Women’s Bathroom – Plumbing, water lines & electrical7/10 Men’s Bathroom – Plumbing, water lines & electrical
7/22
7/22 Front of House – Drywall seams have been sanded. Looks ready for painting!7/22 Back of House – Drywall on the dividing wall is smooth and the back wall is drywalled, too!7/22 Women’s Bathroom – Starting to get the drywall up7/22 Men’s Bathroom – Ducting and sprinklers look to be finished, as well. Looks ready for drywall in here, too!