Landlord work in progress

Some photos of the work in progress. I don’t know about you, but I’m starting to really get a feel for how the space is going to turn out.

6/22

20150622_120741
6/22 Front of House – Demo still progressing, the plastic sheeting is down and their cleaning up the ceiling tiles and wiring and such.
20150622_120706
6/22 Back of House – Demo of the back area that’s going to become the bathroom is pretty much done. They’re starting to get down to the supports in the walls.

6/28

20150628_152753
6/28 Front of House – Supports are now all stripped down, and the framing is up for the dividing wall!
20150628_152833
6/28 Back of House – Bathroom door has been cut, and the first slab cuts have been done. You can see one square area of the floor is up.

7/1

20150701_172500
7/1 Front of House – Not much new work done here
20150701_172529
7/1 Back of House – All of the flooring has been cut, and the trenching is all dug. You can’t see it much, but the piping for the sewer lines is just about complete in the trenches.

7/10

20150710_120712
7/10 Front of House – Drywall is up on the far side.
20150710_120852
7/10 Back of House – The sewer and water lines are done, and the concrete has been poured to fill the trenches in.